IT Strategic Plan
MCC with help of Sungard Higher Education will start developing their three-year IT Strategic Plan October 2006. There will be four sessions -- please see the dateline below. All the notes and relevant information will be posted here.
IT Strategic Planning Dateline
Sept 13th -- Send out survey to faculty and staff
Sept 30th -- Survey will be due
Full TTNA Report
Full ATNA Report
Highlights of both Reports
Oct 18th -- First IT Strategic Planning session
Nov 1st -- Second IT Strategic Planning Session
Nov 15th -- Third IT Strategic Planning Session
Nov 29th -- Fourth and Final IT strategic Session
Mid Dec -- First draft of IT strategic Plan
January 3rd -- Final Draft to MCC
Oct 18th -- First IT Strategic Planning session
Nov 1st -- Second IT Strategic Planning Session
Nov 15th -- Third IT Strategic Planning Session
Nov 29th -- Fourth and Final IT strategic Session
Mid Dec -- First draft of IT strategic Plan
January 3rd -- Final Draft to MCC
The sessions are on Wednesdays and will be four hours long. The sessions will go from 1:00 to 5:00 p.m.
IT Strategic Planning Team:
- Cabinet
- Information Technology Council
- Faculty
- Staff
- Students
- Board Of Trustees
- Representative from 4 years college on campus
- Community Member