MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

Sturrus Technology Center - November 2017

Sturrus Technology Center

(opened Fall 2017)

 

 

 

 

Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening Winter 2019)

 

 

 

 

MCC Arts and Humanities Center Rendering

MCC Arts and Humanities Center

MCC Arts and Humanities Center
(opening Summer 2019)

 

 

 

 

For more information, contact:

John Selmon, Provost and Executive Vice President
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Physical Plant
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through August 3, 2018

Science Center –
$9.6 million
Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Sturrus Technology Center – $14.81 million Arts and Humanities Center – $9 million
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • $6.1 million – millage
  • $5.6 million – State of MI capital outlay
  • $2.4 million –  November 2017 bond issuance

 

  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 million EDA Grant)
  • $4.1 million MEDC Equipment Only Grant in addition to construction budget
  • $6.1 million – millage
  • $2.9 million – Nov. 2017 bond issuance
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: Clark Construction
Latest Accomplishments
  • Completed on August 24, 2015
Construction to Date

  • Site sidewalks are complete
  • Gym floor installation  has begun
  • Basketball hoops are installed
  • Painting of gym is 70% complete
  • A/C is on in the building
  • Tiling in all bathrooms is complete
  • Casework in Area C is complete
  • Top soil is 95% complete
  • Polished concrete is ready for final coat
  • Area A doors have been installed
  • Coping and gutters have been installed on roof
  • Completed on January 11, 2018
Construction to Date

  • Interior demolition of existing maintenance building is complete
  • Underground plumbing rough-in is complete in Area D
  • Electrical overhead rough-in is complete
  • Gas pipe has been cut and capped
  • 3 hr masonry wall between Automotive and Facilities Management has been constructed
  • Mezzanine removal in Areas A and B are completed
  • Metal Stud framing complete – Area D
  • Mezzanine metal decking is complete
Next Steps
Projected Construction for the next Month:

  • Landscaping will begin
  • Wood flooring for gym will be complete
  • Cloud ceiling will be complete
  • Entire gym will be painted
  • Interior metal composite panels will  be installed
  • Headwalls for ICUs will be installed
  • Begin installation of rubber flooring for track
  • Install interior glazing
Projected Construction for Next Month:

  • Complete demolition in Areas A and B
  • Finish and paint Area D
  • Place concrete decking and fire-retardant plywood on mezzanine
  • Install door/window frames and glazing – Area D
  • Hang doors/hardware Area D
  • Install resinous flooring – Area D
  • Install new overhead door – Area D
  • Metal stair installation – Area D
  • Install rubber flooring – Area D
  • Install ceramic tile in Area D bathrooms
  • Install drop ceilings – Area D
  • Complete MEP rough-ins and finishes
  • Install oil separator
  • Place miscellaneous concrete stoops and mechanical pad
  • Complete connections to MEP equipment
Remaining Timeline
  • Winter 2019: Building opening
  • Fall 2018 – Auto renovations completed
  • Summer 2019 – Tech building renovation completed for Fall 2019 start
  • Fall Semester 2019 – Theater renovations completed pending fundraising