MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

Sturrus Technology Center - November 2017

Sturrus Technology Center

(opened Fall 2017)

 

 

 

 

Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening Winter 2019)

 

 

 

 

MCC Arts and Humanities Center Rendering

MCC Arts and Humanities Center

MCC Arts and Humanities Center
(opening Summer 2019)

 

 

 

 

For more information, contact:

John Selmon, Provost and Executive Vice President
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Building Projects
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through September 30, 2018

Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Arts and Humanities Center – $9 million Sturrus Technology Center – $14.81 million Science Center –
$9.6 million
  • $6.1 million – millage
  • $5.6 million – State of MI capital outlay
  • $2.4 million –  November 2017 bond issuance

 

  • $6.1 million – millage
  • $2.9 million – Nov. 2017 bond issuance
  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 million EDA Grant)
  • $4.1 million MEDC Equipment Only Grant in addition to construction budget
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: Clark Construction
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
Latest Accomplishments
Construction to Date

  • Site sidewalks are complete
  • Gym wood floor is compete (Paint to follow)
  • Basketball hoops are installed
  • Painting of gym is complete
  • A/C is on in the building
  • Tiling in all bathrooms is complete
  • Casework in Area C is complete
  • Polished concrete is complete
  • Area A doors have been installed
  • Coping and gutters have been installed on roof (Heat trace to follow)
  • All interior glazing has been installed
  • One-way glass for ICUs has been installed
  • Carpeting in Area C is installed
  • Headwalls for ICUs installed
  • Top soil and landscaping are installed with fire lane
  • “Cloud” ceiling plywood 95% complete
  • Metal lockers installed in locker rooms
  • All interior glass installed
  • All roofing complete
  • Flooring in all areas complete
  • Concrete polishing in corridors is complete
  • PEA flooring installed. Gym equipment in place
  • Radius curtain installed in gym
  • Track painted and striped
  • HUB desk installed
  • TB Brackets installed
  • Wood locker installed
Construction to Date

  • Interior demolition of existing maintenance building is complete
  • Underground plumbing rough-in is complete in Area D
  • Electrical overhead rough-in is complete
  • Gas pipe has been cut and capped
  • 3-hour masonry wall between Automotive and Facilities Management has been constructed
  • Mezzanine removal in Areas A and B is complete
  • Metal Stud framing complete – Area D
  • Mezzanine metal decking complete – Area D
  • Slab on deck complete for Mezzanine in Area D
  • Paint and MEP finishes are 92% complete. (Waiting on Mechanical unit)
  • Flooring has been placed throughout Area D
  • Light fixtures installed in Area D
  • Areas A and B Demolition is complete
  • Window frames, windows, door frames and doors have been installed in Area D
  • New overhead door installed in Area D
  • Installed ceramic tile in Area D bathrooms
  • Installed metal stair Area D
  • Installed concrete in Area B
  • Underground plumbing and electrical complete
  • Underground DEMO complete
  • Exterior brick and block infill complete
  • Completed connections to HVAC units – Area D
  • Completed on January 11, 2018
  • Completed on August 24, 2015
Next Steps
Projected Construction for the next Month:

  • “Cloud” ceiling wood paneling to be complete (90%)
  • Gym floor to be painted
  • Install interior perimeter netting in gym
  • Install all resilient base
  • Install window privacy curtains
  • Install solid surface benches
  • October 4th – The Collaborative final punch list
  • Clark turnover and submit owner’s manual
Projected Construction for Next Month:

  • Measure for aluminum storefront framing
  • Metal stud framing Area B
  • HVAC duct work Area B
  • Infill concrete in Area A
  • Remove pits in Area A
  • Construct Area A canopy
  • Final punch list for Progressive AE Area D – October 1
  • Install structural steel around window openings and RTU openings
  • Begin footing for ramp Area A
  • Complete DEMO (95%)
Remaining Timeline
  • Winter 2019: Building opening
  • Summer 2019 – Tech building renovation completed for Fall 2019 start
  • Fall Semester 2019 – Theater renovations completed pending fundraising