MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

Sturrus Technology Center - November 2017

Sturrus Technology Center

(opened Fall 2017)

 

 

 

 

Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening Winter 2019)

 

 

 

 

MCC Arts and Humanities Center Rendering

MCC Arts and Humanities Center

MCC Arts and Humanities Center
(opening Summer 2019)

 

 

 

 

For more information, contact:

John Selmon, Provost and Executive Vice President
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Building Projects
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through December 7, 2018

Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Arts and Humanities Center – $9 million Sturrus Technology Center – $14.81 million Science Center –
$9.6 million
  • $6.1 million – millage
  • $5.6 million – State of MI capital outlay
  • $2.4 million –  November 2017 bond issuance

 

  • $6.1 million – millage
  • $2.9 million – Nov. 2017 bond issuance
  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 million EDA Grant)
  • $4.1 million MEDC Equipment Only Grant in addition to construction budget
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: Clark Construction
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
Latest Accomplishments
  • Punch list items are underway
Construction to Date

(Area A – Music, Area B – Art, Area D – Auto)

  • Began infilling concrete in Area A
  • Completed footing/foundation placement for ramp
  • Metal stud framing completed in Area B
  • Mechanical, Electrical and Plumbing  rough-ins nearing completion in Area B
  • Placed plywood on face of exterior canopy
  • Installed steel for Roof Top Units
  • Removed oil pits in old automotive wing
  • Completed Demo
  • Completed Area A concrete ramp
  • Began drywall installation in Area B
  • Installed temporary enclosures on exterior of building
  • Continuing installation of curtain walls on Areas A and B
  • Began fire suppression rough-in
  • Completed on January 11, 2018
  • Completed on August 24, 2015
Next Steps
Projected Construction for the next Month:

  • Clark to complete Punch List
Projected Construction for Next Month:

  • Wood Trucking to bring water main into building
  • Complete drywall in Area B
  • Begin drywall in Area A
  • Complete framing in Area A
  • Place concrete stairs and miscellaneous infills
  • Complete all rough-ins in Area B
  • Start drywall finishing Area B
  • Begin installing tile in Area B bathrooms
Remaining Timeline
  • Winter 2019: Building opening Jan. 3, 2019 after the Grand Opening was held Nov. 27, 2018
Summer 2019: Art ans Music Building renovation completed for Fall 2019 building opening

Fall Semester 2019: Theater renovations completed pending fundraising