MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

CenterImageUpdated

 

 

 

 

 

 

View a live webcam of the Science Center construction 

Listen to how the new Science Center will make a difference:

For more information, contact:

John Selmon, Vice President for Student Services and Administration
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Physical Plant
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

Friday Tours (May 1-August 31)

Every Friday from May 1 through August 31, MCC will host public tours of both its new Science Center next to the Stevenson Center on campus and of its Downtown Center, the former Chronicle Building. Both facilities are currently undergoing construction and/or renovations. The tours will be held from 1:30-3:30 p.m., as well as by appointment.  Please stop by to learn how Muskegon Community College is helping meet the talent needs of the 21st century. For more information, call the office of Dr. John Selmon, VP for Student Services and Administration, at (231) 777-0266.

 

Building Projects At-a-Glance through May 11, 2015

Science Center
$9.6 Million (DTMB $4.6)
Health and Wellness Center
$6.2 Million
Downtown Center
$11.3 Million
($4.1 MEDC Grant)
Arts Center
$6.1 Million
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
  • Architect: TBD
  • Construction: TBD
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: TBD
  • Architect: TBD
  • Construction: TBD
Latest Accomplishments
Completed Work Science Center Addition Phase I:

  • Completed MEP Overhead rough in
  • Completed polishing and sealing concrete floors
  • Ceilings are 30% installed
  • Painting of all CMU walls is 85%
  • Metal wall panels are 75% installed
  • Roofing trim metal is installed on all roofs
  • Completed exterior sidewalks and stoops
  • Geothermal wells 70% completed
  • Completed the cast stone and interior brick
  • Completed curtain wall system
  • Interior lighting is 35% installed
  • Hard tile is 75% installed
  • DA Central installed all the wire for the system
  • Roughed in exhaust arms in all lab space

Completed Work Science Center Addition Phase II:

  • Construction has started with the demolition of casework, interior walls, and MEP disconnect and removal
  • Submittals have been requested from each trade contractor and some have started to come in
  • Asbestos abatement has started and is completed in the respiratory area
  • Temporary construction walls have been installed on the project
  • Received RFPs on May 4, 2015 from four Managed Services vendors for the Health and Wellness Center Project:
    • Centers
    • Power Wellness
    • YMCA
    • MediFit
  • Submitted an Economic Development Administration (federal agency) Grant for renovations on March 12, 2015
  • Responded to EDA with additional information re: grant submission at the end of March 2015
  • Currently meeting with departmental heads from College program areas to finish programming of Applied Technology equipment and Masonic Temple. Programming phase scheduled to be completed at end of Schematic Design Phase due to recent addition of Masonic Temple into the program
  • Ongoing existing building verification and development of Building Information Model (BIM) for use in future design and documentation phases,
  • Summary of Programming Needs – completed draft
  • Established a series of meetings
Next Steps
NEXT MONTH:Phase I:

  • Complete MEP final connections
  • Complete ceilings
  • Complete finished painting of all CMU walls and drywall walls
  • Rework tie-in overhangs
  • Complete metal wall panel installation
  • Complete roofing trim metal on all the metal panels
  • Install geothermal wells complete
  • Install Grow Room walls and ceiling finished materials
  • Install exterior aluminum doors and slider doors
  • Start up the mechanical system for testing
  • Complete the lighting installation
  • Paint metal deck and install accoustical ceiling spray
  • Start delivery of casework and tops for the project
  • Install lab hoods

 

NEXT MONTH Phase II – STEM Center Redesign

  • Install interior walls and drywall Respiratory Area
  • Start overhead and under floor rough-ins
  • Interior wall rough-ins
  • Installation of metal door frames
  • Start the installation of ceilings
  • Patch and paint walls
  • Start flooring
  • Measure for casework and interior finishes

NEXT MONTH Phase III – Mechanical Upgrades

  • Bid out Phase II on May 27, 2015 at 11:00 a.m.
  • Get Board approval June 3, 2015
  • Contracts out before June 10, 2015
  • Start construction June 17, 2015
  • Review RFPs, interview vendors, and make a recommendation to the MCC Board of Trustees by May 20, 2015 board meeting
  • Continue developing new academic and athletic programs for Health and Wellness Center
  • July/August 2015 – engage construction company

 

  • EDA notified MCC of grant approval. Verification process for actual grant monies has begun
  • Schematic Plan development has identified 85% of program spaces in Chronicle building. Walk through scheduled for week of 5/11/15 for identification of historic elements to preserve/reuse.
  • Assessments/survey work of Masonic Temple beginning in May. Program elements of Archives, Entrepreneurial Program and Black Box Theater tentatively identified as occupants of Masonic Temple.
  • Develop an initial equipment list – ongoing
Remaining Timeline
Phase I:

  • Completion of the Science Center addition is still on schedule to be completed in July 2015.

Phase II:

  • Completion of STEM Center Redesign renovations by late August 2015

Phase III:

  • Completion of Mechanical Upgrade by late August 2015
  • September 2016 – complete new Health and Wellness Center addition and renovations of existing gym.

 

  • June/July 2015: Board approval of schematic design. Mid June scheduled for completion of Schematic Design and programming. Design team working to incorporate Masonic Temple scope addition into current timeline in order to maintain January 2016 for bidding of project.
  • December 2015: Construction documents completed
  • January 2016: Bidding Phase
  • Depending upon final scope of work, EDA grant funding process and construction schedule, some areas of project could be open by September 2016.
  • Spring 2017 – project completed and handed over to owner
  • Summer 2017 – owner move in, training and program shakeout
  • Fall 2017 – Classes begin building wide
  • Plan to seek architectural services as early as June/July 2015
  • Winter 2016 – begin renovation work in Tech Building
  • Summer 2016 – begin renovation work in Theater, Music, Arts, etc.
  • Fall 2016 – well underway, near completion.

 

DCIM100GOPROG0030123.

MCC Downtown Center

 

 

 

 

 

 

 

 

 

The Vision

Science, Technology, Engineering, and Math (STEM) Center

What
New and renovated classroom and laboratory space for the life and physical sciences. The completed project will serve a combined 18 academic programs and will renovate existing lab and instructional space, as well as construct new space adjacent to the Stevenson Center for Higher Education.

Why
“Muskegon Community College needs to compete on a national and global level,” said Nesbary. “In addition to meeting crucial student needs, this expansion will also benefit employers and the community at large. It will help attract and retain talented individuals and equip them with the science skills to make them both more effective employees and informed residents, critical to improving the overall health of our communities. Moreover, the College’s growth from approximately 2,000 in the mid-1960s to approximately 5,000 credit-bearing students has led to the need for additional academic space in the STEM fields.”

Where
Renovation of existing space in the Main Building, along with a 19,000 sq. ft. new building adjacent to the Stevenson Center for Higher Education

When
Groundbreaking for the new building will take place on Sept. 3, 2014, with full occupancy expected in August 2015. Reconstruction of existing space is expected to begin in Spring 2015, with completion expected in mid-2016.

Cost
$9.6 million, $4.65 million of which comes from a state appropriation and the remainder from property tax revenues approved in the November 2013 general election. On July 3, 2013, Gov. Snyder signed a supplemental appropriations bill authorizing MCC to develop planning documents for 33,000 sq. ft. of existing and expanded campus facilities. The new law authorized MCC to begin planning for the project. On March 14, 2014 Lt. Gov. Brian Calley signed PA 301 of 2014, legislation authorizing MCC to construct a 25,000-square-foot science laboratory and renovate 20,000 square feet of existing science facilities.

 

MCC Downtown Center

What
The MCC Downtown Center will house the College’s applied technology programs, including computer aided design, computer aided manufacturing, engineering, and electronics. A maker space, available to the community, will connect regional engineers, manufacturers, artists, and creative makers/thinkers to the college. Plans also include entrepreneurial programs, experiential learning programs and a black box meeting/performance space to serve our students and community.

Why
“Many colleges around the nation and in Michigan have partnered with their communities to grow the local economy and just as importantly, to serve the needs of students, business and the community,” explains MCC President Dale K. Nesbary. Since moving to its current campus at Marquette and Quarterline, MCC’s enrollment has strained its existing facilities by growing from approximately 2,000 credit-bearing students to roughly 5,000 students, with another 2,000-plus students engaging in lifelong learning and training programs. The College has also increased programming in manufacturing, design, engineering, welding, technology, and related fields and has greatly expanded partnerships with the business community.

Where
In heart of historic downtown Muskegon at 981 Third Street, site of the former Muskegon Chronicle Building.

When
By mid-2016. Planning and programming for the site are nearing completion. The site acquisition is complete and design process has begun.

Cost
$7.2 million

 

Health and Wellness Center

What
A major renovation and expansion of the Bartels-Rode Gymnasium and Health Center will update one of the two oldest and most popular buildings on the MCC Campus. Included are a new recreation floor area, fitness center, classrooms and training space that collectively serve 10 academic areas.

Why
Currently 46 years old, Bartels-Rode Gymnasium is the most heavily used facility at MCC. “Our 150 percent growth as a campus since 1968, has taken the most wear and tear on our over-used health and recreation facilities,” explained Nesbary. “It is expected that the new fitness and health facilities will generate operational revenue to offset increased costs associated with the additional building space.

Where
An expansion of the existing Bartels-Rode Gymnasium and Health and Wellness Center.

When
Expected completion in mid-2016.

Cost
$6.2 million

Size
17,599 sq. ft. of new space and 12,800 sq. ft of renovated space

 

Creative and Performing Arts Center

What
The proposed $6.1 million arts center includes five new art studios, three classrooms, an exhibition gallery and kiln room, improvements to the Overbrook Theater and performance space, and expanded lab and multimedia instructional space. This space will serve MCC’s growing visual arts, performing arts and communications programs. The Visual Arts program would be relocated in an expansion of the existing Overbrook Theater. The Music, Theater, and Communications programs would occupy existing space, along with minimal expansion to accommodate program growth.

Why
In the early 1970s, MCC placed its creative arts program in a “temporary” facility, a free-standing pole barn at the far corner of the north parking lot. The program is still located in that pole barn, with its inadequate cooling, heating, lighting, storage and demonstration space. The site’s limitations negate year-round and evening instruction.

“Muskegon County has a rich and proud history not only of supporting the arts, but also of producing its own talented artists, many of whom make their living operating small studios in our communities” explained Nesbary. Muskegon County is home to many exceptional arts institutions, including the Muskegon Museum of Art, the internationally recognized Blue Lake Fine Arts Camp with its 6,000-plus students annually, and many exceptional scholastic music programs that garner state championships and national attention. “Our faculty and staff are highly skilled, regularly performing locally, regionally, and nationally,” added Nesbary.”

MCC’s arts facilities need to be up to the highest standards to meet the expectations of and continue the educational process for these talented students. We need to keep these students in our community rather than sending them out of the region or state. Upgraded facilities will help us accomplish this goal.

Where
Renovated space on the MCC campus.

When
Mid- to late 2016. An Arts Center Committee comprised of community members, students, faculty, staff, administrators and MCC Board of Trustees members, will finalize planning for the construction and relocation of the MCC Arts and Humanities Department. The Art Center planning process will begin in earnest in May 2014.  It is expected that construction will begin in early to mid-2015, with a target date for completion in mid to late 2016.

Cost
$6.1 million