MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

Downtown Center rendering (updated October 2016)

MCC Downtown Center

MCC Downtown Center

(opening Fall 2017)

 

 

 

 

Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening Summer 2018)

 

 

 

 

MCC Arts and Humanities Center Rendering

MCC Arts and Humanities Center

MCC Arts and Humanities Center
(opening Winter 2018)

 

 

 

For more information, contact:

John Selmon, Vice President for Student Services and Administration
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Physical Plant
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through Jan. 9. 2017

Science Center –
$9.6 million
Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Downtown Center -$14.27 million Arts and Humanities Center – $9 million
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • $6.1 million – millage
  • $5.6 million – Capital Outlay
  • $2.4 million- will seek bond

 

  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 EDA Grant) etc.

$4.1 million MEDC Equipment Only Grant in addition to construction budget

  • $6.1 million – millage
  • $2.9 million -fundraising
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Managed Services Firm: Power Wellness
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: TBD
Latest Accomplishments
 Project completed on August 24, 2015 Health and Wellness Center

  • Submitted Phase 200/300: programming and Schematic Design Summary.
  • Cleared site in preparation for start of construction Spring of 2017.
Construction Progress to Date:

  • 2nd area “B” rough in overhead work is 98%
  • Exterior restoration is 30% complete
  • CMU walls Area “B” 2nd floor is 98% complete
  • Door frames for Area “B” are complete
  • 1st Floor Area B demolition is 98% complete
  • Drywall installation is 96% complete on Area B 2nd Floor
  • Drywall finishing is 96% complete
  • Basement “B” demolition is 90% complete
  • Fire protection 80% installed on the second floor
  • Complete steel framing for AHU’s on roof.
  • Painting in Area B 2nd floor is 60% complete
  • Rough in MEP underground 25% complete
  • CMU walls 1st floor Arae B are 75% complete
  • Ceilings are 10% installed in Area B 2nd floor
  • Presented revised schematic design Nov. 4, 2016 to Arts and Humanities Committee and confirmed project scope to project budget.
Next Steps
Health and Wellness Center

  • Continuing with design development (include simulation lab, given new Capital Outlay Grant approval) for the DMTB 400 Level submission scheduled for January 2017,
  • Seek approval for DMTB to move forward with construction plans for the project by February 1, 2017
  • Continue developing new academic and athletic programs for the Health and Wellness Center
Projected Construction for the Next Month:

  • Complete demolition Area B
  • Complete Metal Stud framing and CMU walls Area B 2nd floor
  • Complete Metal Stud framing and CMU walls Area B 1st floor
  • Complete drywall installation and finishing Area B 1st floor
  • Complete Rough-In MEP & Fire Protection 2nd Floor Area B
  • Complete Rough-In MEP & Fire Protection 1st Floor Area B
  • Finish floor prep on Area B 2nd floor and floor infills
  • Complete Painting 2nd floor Area B 2nd floor in two weeks.
  • Complete ceiling grid install Area B 2nd floor
  • Complete design development and present to Arts and Humanities Committee on Jan. 13, 2017
Remaining Timeline
Health and Wellness Center

  • Late Spring 2017: Anticipated construction start for the new Health and Wellness Center
  • Summer 2018: Complete new Health and Wellness Center
  • Anticipate Fall of 2017 project completed and handed over to owner. College may have to consider a later move-in date than start of classes due to the length of EDA reviews.
  • Winter 2018: Renovation completed.