MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

Sturrus Technology Center - November 2017

Sturrus Technology Center

(opened Fall 2017)

 

 

 

 

Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening Winter 2019)

 

 

 

 

MCC Arts and Humanities Center Rendering

MCC Arts and Humanities Center

MCC Arts and Humanities Center
(opening Summer 2019)

 

 

 

 

For more information, contact:

John Selmon, Provost and Executive Vice President
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Physical Plant
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through May 4, 2018

Science Center –
$9.6 million
Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Sturrus Technology Center – $14.81 million Arts and Humanities Center – $9 million
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • $6.1 million – millage
  • $5.6 million – State of MI capital outlay
  • $2.4 million – bond issuance

 

  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 million EDA Grant)
  • $4.1 million MEDC Equipment Only Grant in addition to construction budget
  • $6.1 million – millage
  • $2.9 million – Nov. 2017 bond issuance
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: Clark Construction
Latest Accomplishments
  • Completed on August 24, 2015
Construction project to date:

  • Concrete gym flooring is complete
  • Area A (Mercy) section has one coat of finish paint
  • Ceiling grid has begun in Mercy seciton
  • Drywall finishing is complete in ICU Area
  • Main entry curtain wall, North & South curtain walls are installed
  • Metal stud room framing is complete
  • Plumbing rough-in is complete
  • Overhead rough-in is 85% complete
  • Shower rough-in is complete
  • Exterior caulking is complete
  • Completed on January 11, 2018
  • Asbestos abatement has been completed in the vacant Tech Wing
  • Pre-demolition in vacated areas of the Tech Wing is mostly complete
  • Bids were received April 11 and major contracts were approved by the board on April 18, with theater sections and numerous whitebox areas identified for delay to allow for fundraising
Next Steps
Projected Construction for the next month:

  • Insulated metal panel installation will begin on gym
  • Finish sitework will begin
  • Ceramic tiling of bathrooms will begin
  • Siding metal panels will be complete
  • Irrigation will begin
  • Precast stone sills will be installed
  • Clark will execute contracts with subcontractors and work will begin immediately on the Sheet Metal/Maintenance Building and the Overbrook Theater. Full renovation of the tech wing will begin in late summer after automotive moves to the Sheet Metal/Maintenance Building
  • Trade contractor start-up meeting will be held May 7 on site
  • Demolition of the Sheet Metal/maintenance Building will begin in two weeks.
Remaining Timeline
  • Winter 2019: Building opening
  • Fall 2018 – Auto renovations completed
  • Summer 2019 – Tech building renovations completed
  • Fall Semester 2019 – Theater renovations completed pending fundraising