MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

Downtown Center rendering (updated October 2016)

MCC Downtown Center

MCC Downtown Center

(opening Fall 2017)

 

 

 

 

Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening January 2019)

 

 

 

 

MCC Arts and Humanities Center Rendering

MCC Arts and Humanities Center

MCC Arts and Humanities Center
(opening Winter 2018)

 

 

 

 

For more information, contact:

John Selmon, Provost and Executive Vice President
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Physical Plant
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through April 2, 2017

Science Center –
$9.6 million
Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Downtown Center -$14.27 million Arts and Humanities Center – $9 million
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • $6.1 million – millage
  • $5.6 million – Capital Outlay
  • $2.4 million- will seek bond

 

  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 million EDA Grant) etc.

$4.1 million MEDC Equipment Only Grant in addition to construction budget

  • $6.1 million – millage
  • $2.9 million -fundraising
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: TBD
Latest Accomplishments
Project completed on August 24, 2015
  • Working with the State Budget Office on requested revisions for our 200/300 level submittal
Construction Progress to Date:

  • 2nd loor Area B rough in overhead work is 98% complete
  • Exterior restoration is 30% complete
  • CMU walls Area B 2nd floor is 98% complete
  • Basement “B” demolition is completed
  • Fire protection 98% installed on the second floor
  • Painting in Area B 2nd floor is 98% complete
  • Painting in Area B 1st floor is 90% complete
  • Rough in MEP underground area is complete
  • CMU walls 1st floor Area B are completed
  • Ceilings grids are 98% installed in Area B 2nd floor
  • Complete drywall installation and finishing Area B 1st floor
  • Apply K-13 spray in the welding lab
  • Demo Area A is completed
  • Rough in fire protection Temple 1st floor 98% complete
  • Rough in fire protection Temple 2nd floor is completed
  • Elevator foundation is completed
  • Window replacement is completed
  • Historical lobby patching is completed and ready for paint
  • Completed the chiller steel support
  • welding booths are 45% installed
  • Completed design development and presented to Arts and Humanities Committee Jan. 13, 2017
Next Steps
Health and Wellness Center

  • Continuing with design development (include simulation lab, given new Capital Outlay Grant approval) for the DMTB 400 Level submission.
Projected Construction for the Next Month:

  • Complete classroom build our Precast and steel
  • Finish Rough-In MEP & Fire protection 2nd Floor Area B
  • Finish Rough-In MEP & Fire protection 1st Floor Area B
  • Complete Painting Area B 2nd floor
  • Complete ceiling grid install Area B 2nd floor
  • Complete CMU walls for the elevator shaft
  • Install and complete 2nd Floor flooring next to the elevator
  • Complete Area A basement work
  • Complete painting historical lobby and finish woodworking
  • Start and complete Arae A ramp
  • Start Area A 2nd floor steel
  • Start Masonry restoration on the exterior of the building
  • start and complete MEP underground Area A
  • Pour concrete floors infill and foundry pit Area A
  • Select Construction Manager April 2017
  • Complete cost estimate and validate budget
  • Complete Construction documents Fall 2017
Remaining Timeline
Health and Wellness Center

  • Fall 2017: Anticipated construction start for the new Health and Wellness Center
  • January 2019: Complete new Health and Wellness Center
  • Anticipate partial Fall of 2017 project completed and handed over to owner. The “old” Chronicle section should be ready for a fall class start, including welding and CAD, but the “new” Chronicle and former Temple should be complete in November for a January 2018 start to classes,etc.
  • Winter 2018: Renovation completed.