MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

 

Downtown Center rendering (updated October 2016)MCC Downtown Center
(opening Fall 2017)

 

 

 

 

MCC Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening Summer 2018)

 

 

 

 

For more information, contact:

John Selmon, Vice President for Student Services and Administration
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Physical Plant
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through Nov. 4, 2016

Science Center –
$9.6 million
Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Downtown Center -$14.27 million Arts and Humanities Center – $9 million
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • $6.1 million – millage
  • $5.6 million – Capital Outlay
  • $2.4 million- will seek bond

 

  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 EDA Grant) etc.

$4.1 million MEDC Equipment Only Grant in addition to construction budget

  • $6.1 million – millage
  • $2.9 million -fundraising
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Managed Services Firm: Power Wellness
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: TBD
Latest Accomplishments
 Project completed on August 24, 2015 Health and Wellness Center

  • Submitted Phase 200/300: programming and Schematic Design Summary on Nov. 1, 2016.
Construction Progress to Date:

  • 2nd area “B” rough in overhead work is 85%
  • 2nd floor demolition Area “B” is complete
  • Exterior restoration is 30% complete
  • Steel reinforcing Area “B” is complete
  • Metal stud framing Area “B” 2nd floor is complete
  • Metal Stud framing in Temple begun
  • CMU walls Area “B” 2nd floor is 95% complete
  • Door frames for Area “B” is 95% complete
  • 1st Floor Area B demolition is 95% complete
  • Demolition of exterior wall on Clay Ave. is complete
  • Masonic Temple demolition is complete
  • Drywall installation is 85% complete on Area B 2nd Floor
  • Drywall finishing is 70% complete
  • Basement “B” is 90% complete
  • Roof replacement is 70% complete
  • Fire protection has begun
  • All door frames are delivered to the site.
  • Reviewed and revised budget with Arts and Humanities Committee on Nov. 4, 2016.
Next Steps
Health and Wellness Center

  • Waiting on approval of Phase 200/300: programming and Schematic Design Summary that was submitted on Nov. 1, 2016.
  • Seek approval for the DMTB to move forward with construction plans for the project by February 1, 2017
  • Continue developing new academic and athletic programs for the Health and Wellness Center
Projected Construction for the Next Month:

  • Complete demolition all areas
  • Complete steel framing for AHU’s on roof
  • Complete Area B roofing
  • Complete Metal Stud framing and CMU walls Area B 2nd floor
  • Complete Metal Stud framing and CMU walls Area B 1st floor
  • Complete drywall installation and finishing Area B 1st floor
  • Complete Rough-In MEP & Fire Protection 2nd Floor Area B
  • Start Rough-In MEP & Fire Protection 1st Floor Area B
  • Start floor prep on Area B 2nd floor and floor infills
  • Continue working on the Schematic Design
Remaining Timeline
Health and Wellness Center

  • Late Spring 2017: Anticipated construction start for the new Health and Wellness Center
  • Summer 2018: Complete new Health and Wellness Center
  • Anticipate Fall of 2017 project completed and handed over to owner. College may have to consider a later move-in date than start of classes due to the length of EDA reviews.
  • Winter 2018: Renovation completed.