MCC Master Plan Construction Update

Supported by the taxpayers of Muskegon County

 

MCC Science Center

MCC Science Center

MCC Science Center
(opened Fall 2015)

 

 

 

Sturrus Technology Center - November 2017

Sturrus Technology Center

(opened Fall 2017)

 

 

 

 

Health and Wellness Center

MCC Health and Wellness Center

MCC Health and Wellness Center
(opening Winter 2019)

 

 

 

 

MCC Arts and Humanities Center Rendering

MCC Arts and Humanities Center

MCC Arts and Humanities Center
(opening Summer 2019)

 

 

 

 

For more information, contact:

John Selmon, Provost and Executive Vice President
Phone: (231) 777-0265 Email: john.selmon@muskegoncc.edu

Gerald Nyland, Director of Physical Plant
Phone: (231) 777-0315  Email: gerald.nyland@muskegoncc.edu

 

Building Projects At-a-Glance through February 13, 2018

Science Center –
$9.6 million
Health and Wellness Center & Lakeshore Fitness Center – $14.1 million Sturrus Technology Center – $14.81 million Arts and Humanities Center – $9 million
  • $4.6 million – State of Michigan DTMB
  • $4.6 million – millage
  • $400,000 – MCC
  • $6.1 million – millage
  • $5.6 million – capital outlay
  • $2.4 million – will seek bond

 

  • $7.2 million – millage
  • $7.07 million – donations, grants (including $2.51 million EDA Grant)
  • $4.1 million MEDC Equipment Only Grant in addition to construction budget
  • $6.1 million – millage
  • $2.9 million – bond issuance
  • Architect: Kingscott/BMA
  • Construction: Clark Construction
  • Architect:The Collaborative
  • Construction: Clark Construction
  • Architect: C2AE/MMA/Prein Newhof
  • Construction: Clark Construction
  • Architect: Progressive AE
  • Construction: Clark Construction
Latest Accomplishments
  • Project completed on August 24, 2015
  • Area A & C is temporarily enclosed
  • Area A & C steel and decking is complete
  • Overhead water  copper piping is 80% complete
  • Overhead duct work has begun
  • Temporary heaters have been installed and are running
  • Roofing on Area A & C is 50% complete
  • Rooftop units have been set on roof curbs
  • Screenwall framing on roof is complete
  • Brick on exterior is 50% complete
  • Successful Grand Opening was held January 11
  • Machine move-in completed Jan. 31 and the window wall along Fourth Street has been reinstalled
  • Ongoing meetings to finalize bid documents by early March to solicit bids at that time and award bids around May 1..
Next Steps
Projected Construction for the next month:

  • Brick will be complete
  • Area A& C slabs on grade will be poured
  • All overhead rough-in of mechanical piping will be complete
  • Gas piping on roof to rooftop units will be complete
  • Gym steel will be set
  • Interior framing will have begun
  • Electrical overhead will begin
  • Windows will be installed
Projected Construction for the next month:

  • Completed hook-ups of machine lab equipment
  • Complete construction and bid documents and go for bid.
Remaining Timeline
  • Winter 2019: Building opening
  • Completed
  • Summer 2019: Renovation completed.